2018/01/06
Duration: 60 min.
Starts at: 21:00 GMT
Ends at: 22:00 GMT

Our System Administrators will perform a kernel upgrade on servers in the datacenters in Bulgaria and Hong Kong. The upgrade procedure requires a server reboot, and brief outages (up to five minutes) may occur.

2018/01/07
Duration: 60 min.
Starts at: 09:00 GMT
Ends at: 10:00 GMT

Our System administrators will perform a kernel upgrade on servers in the US datacenter. The upgrade procedure requires a server reboot, and brief outages (up to five minutes) may occur.

Hardware maintenance for servers in the European datacenter
Our system administrators scheduled a hardware maintenance for servers:

s803.sureserver.com,
s807.sureserver.com,
s1801 - s1820.

The maintenance will occur as follows:

Maintenance start time: Dec 8, 2017, 17:00 EST
Maintenance end time: Dec 8, 2017, 19:00 EST
Expected service outage: up to 15 minutes

The purpose of the maintenance is a hardware upgrade.

Hardware maintenance for servers at the iAdvantage datacenter (HK)
Our system administrators scheduled a hardware maintenance for servers:

server209-station212,
station171-station175,
host201-host206,
hosting334,
domain50,
webmachine101,
thehosting123,
hostsolution737,
hoster900,
system447,
serversys852,
hostcompany100,
website12,
machine36.

The maintenance will occur as follows:
Maintenance start time: Nov 19, 2017, 00:00 HKT
Maintenance end time: Nov 19, 2017, 06:00 HKT
Expected service outage: up to 25 minutes for each server

The purpose of the maintenance is to complete a hardware upgrade, which will require a server reboot.

Hardware maintenance for servers at the iAdvantage datacenter (HK)
Our system administrators scheduled a hardware maintenance for servers:

s213.sureserver.com,
s214.sureserver.com,
s215.sureserver.com,
s222.sureserver.com,
s223.sureserver.com,
s224.sureserver.com.

The maintenance will occur as follows:
Maintenance start time: Nov 19, 2017, 00:00 HKT
Maintenance end time: Nov 19, 2017, 06:00 HKT
Expected service outage: up to 20 minutes for each server

The purpose of the maintenance is to complete a hardware upgrade, which will require a server reboot.

Hardware maintenance for servers at the iAdvantage datacenter (HK)
Our system administrators scheduled a hardware maintenance for servers:

s1561-s1600.

The maintenance will occur as follows:
Maintenance start time: Nov 18, 2017, 02:00 HKT
Maintenance end time: Nov 18, 2017, 06:00 HKT
Expected service outage: up to 15 minutes for each server

The purpose of the maintenance is to complete a hardware upgrade, which will require a server reboot.

Hardware maintenance for servers at the iAdvantage datacenter (HK)
Our system administrators scheduled a hardware maintenance for servers:

station176-station198,
host201-host206,
server256,
server208.

The maintenance will occur as follows:
Maintenance start time: Nov 18, 2017, 00:00 HKT
Maintenance end time: Nov 18, 2017, 06:00 HKT
Expected service outage: up to 25 minutes for each server

The purpose of the maintenance is to complete a hardware upgrade, which will require a server reboot.

Hardware maintenance for servers at the iAdvantage datacenter (HK)
Our system administrators scheduled a hardware maintenance for servers:

s216.sureserver.com,
s217.sureserver.com,
s218.sureserver.com,
s219.sureserver.com,
s220.sureserver.com,
s221.sureserver.com.

The maintenance will occur as follows:
Maintenance start time: Nov 18, 2017, 00:00 HKT
Maintenance end time: Nov 18, 2017, 06:00 HKT
Expected service outage: up to 20 minutes for each server

The purpose of the maintenance is to complete a hardware upgrade, which will require a server reboot.

About eHosted

eHosted has been in the web and Email hosting business since 1997 with many customers that have been with us since the beginning!

Resources